Project Risk

MGT 640 Topic 4, Project Risk Assessment Problems SOLUTION
ID Task Optimistic Duration (days) Most Likely Duration (days) Pessimistic Duration (days) PERT Expected Duration (days) Critical Path Variance
1 TECHNOLOGY REFRESH (VERSION B) PROJECT
2 Initiating
3 Meet with key stakeholders 2 3 12 4
4 Finalize statement of work 2 10 15 10
5 Secure project team leads 2 2 4 2
6 Finalize stakeholder register 2 10 13 9
7 Develop project charter 2 5 17 7
8 Finalize project charter 2 4 8 4
9 Planning
10 Scope Planning
11 Requirements
12 Develop/finalize functional requirements 10 18 28 18
13 Develop/finalize hardware requirements 12 16 18 16
14 Develop/finalize software requirements 10 16 30 17
15 Develop/finalize requirements traceability matrix 11 14 28 16
16 Finalize project deliverables 2 2 3 2
17 Develop scope statement 4 9 10 8
18 Finalize/Update WBS 2 3 5 3
19 Schedule (Time) and Cost Planning
20 Finalize hardware/software costs 2 4 5 4
21 Update activities and duration estimates 6 12 14 11
22 Human Resource Planning
23 Finalize resource requirements 6 10 14 10
24 Finalize project costs 4 11 19 11
25 Identify training requirements 2 4 5 4
26 Complete training activities 6 12 14 11
27 Quality Planning
28 Determine impacted quality processes 2 3 4 3
29 Finalize quality management plan 2 10 18 10
30 Risk Planning
31 Update project risks 3 6 12 7
32 Draft risk register 2 3 8 4
33 Finalize risk management plan 2 4 7 4
34 Finalize Project Plan
35 Finalize communications management plan 2 3 4 3
36 Finalize procurement management plan 2 6 14 7
37 Finalize stakeholder management plan 2 2 5 3
38 Finalize project schedule/cost baseline 2 13 19 12
39 Finalize project plan 2 5 16 6
40 Obtain approval for project plan 2 4 7 4
41 Executing
42 Hardware
43 Procure hardware from suppliers 10 24 32 23
44 Software
45 Obtain software OS licenses 6 11 20 12
46 Obtain software application licenses 6 8 17 9
47 Pilot Testing
48 Setup test area 1 2 2 2
49 Load software onto pilot machines 4 6 8 6
50 Validate functionality 3 6 8 6
51 Deployment
52 Configure production hardware 10 25 33 24
53 Deploy production hardware 11 19 23 18
54 Load software to deployed hardware 12 17 19 17
55 Testing
56 Validate startup on deployed hardware 4 9 18 10
57 Perform OS testing 4 8 17 9
58 Perform application testing 4 19 28 18
59 Obtain formal sign-off from users 6 17 24 16
60 Monitoring and Controlling
61 Formal Customer Review 1
62 Hold formal customer review after project plan approval 1 3 4 3
63 Update project plan 4 10 20 11
64 Formal Customer Review 2
65 Obtain updates regarding key deliverables from project team 5 18 22 17
66 Hold formal customer review after pilot testing 5 7 11 7
67 Update project plan 4 8 15 9
68 Closing
69 External
70 Finalize procurement with suppliers 5 18 24 17
71 Customer Approval
72 Hold final customer review 1 2 2 2
73 Prepare/submit final customer report 3 6 10 6
74 Audit against contractual deliverables 3 5 8 5
75 Obtain final customer approval 2 3 4 3
76 Internal
77 Hold lessons learned meeting 1 1 1 1
78 Update final internal report 4 6 12 7
79 Hold project team celebration event 1 1 2 1
Expected Project Finish Time: Total Critical Path Variance: days
days
Total Critical Path Standard Deviation: days
Probability of finishing the project in 287 days is
or
%
Probability of finishing the project in 273 days is
or
%

The post articlewritingcafe.com – MGT640Topic4ProjectRiskAssessmentProblemsTEMPLATE.xls appeared first on Articlewritingcafe.

GET HELP WITH YOUR HOMEWORK PAPERS @ 25% OFF

For faster services, inquiry about  new assignments submission or  follow ups on your assignments please text us/call us on +1 (251) 265-5102

Write My Paper Button

WeCreativez WhatsApp Support
We are here to answer your questions. Ask us anything!
👋 Hi, how can I help?
Scroll to Top