Project Management
James B. Christa
Columbia Southern University
4. Project Schedule
4.1 Activity Duration Estimates (days)
Activity Number |
Activity |
Predecessor |
Optimistic duration |
Most likely duration |
Pessimistic duration |
Estimated duration |
1 |
Notify Stakeholders |
– |
1 |
1 |
1 |
1 |
2 |
Estimate the cost |
1 |
1 |
1 |
1 |
1 |
3 |
Establish starting date |
1,2 |
1 |
1 |
1 |
1 |
4 |
Engage the project team |
3 |
2 |
2 |
2 |
2 |
5 |
Assess the available resources |
4 |
7 |
5 |
8 |
7 |
6 |
Identify suppliers |
4,5 |
7 |
5 |
7 |
7 |
7 |
Purchase equipment |
6 |
5 |
5 |
10 |
5 |
8 |
Install devices |
7 |
21 |
20 |
28 |
21 |
9 |
Test the system |
7,8 |
14 |
14 |
14 |
14 |
10 |
Hand over the project |
9 |
1 |
1 |
1 |
1 |
Critical Path
12345678910
1+1+1+2+7+7+5+21+14+1=60
The critical path is
12345678910
It takes 60 days, the longest duration.
4.2 Gantt Chart
Task |
Status |
|||||||
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
Week 7 |
Week 8 |
|
Notify Stakeholders |
||||||||
Estimate the cost |
||||||||
Establish starting date |
||||||||
Engage the project team |
||||||||
Assess the available resources |
||||||||
Identify suppliers |
||||||||
Purchase equipment |
||||||||
Install devices |
||||||||
Test the system |
||||||||
Hand over the project |
4.3 Activity Network
Activity |
Predecessor |
Duration |
Notify Stakeholders |
– |
1 |
Estimate the cost |
1 |
1 |
Establish starting date |
1,2 |
1 |
Engage the project team |
3 |
2 |
Assess the available resources |
4 |
7 |
Identify suppliers |
4,5 |
7 |
Purchase equipment |
6 |
5 |
Install devices |
7 |
21 |
Test the system |
7,8 |
14 |
Hand over the project |
9 |
1 |
The post UnitVcourseProject.doc appeared first on School Core.