MGT 640 Topic 4, Project Risk Assessment Problems SOLUTION | ||||||||
ID | Task | Optimistic Duration (days) | Most Likely Duration (days) | Pessimistic Duration (days) | PERT Expected Duration (days) | Critical Path | Variance | |
1 | TECHNOLOGY REFRESH (VERSION B) PROJECT | |||||||
2 | Initiating | |||||||
3 | Meet with key stakeholders | 2 | 3 | 12 | 4 | √ | ||
4 | Finalize statement of work | 2 | 10 | 15 | 10 | √ | ||
5 | Secure project team leads | 2 | 2 | 4 | 2 | |||
6 | Finalize stakeholder register | 2 | 10 | 13 | 9 | √ | ||
7 | Develop project charter | 2 | 5 | 17 | 7 | |||
8 | Finalize project charter | 2 | 4 | 8 | 4 | √ | ||
9 | Planning | |||||||
10 | Scope Planning | |||||||
11 | Requirements | |||||||
12 | Develop/finalize functional requirements | 10 | 18 | 28 | 18 | √ | ||
13 | Develop/finalize hardware requirements | 12 | 16 | 18 | 16 | |||
14 | Develop/finalize software requirements | 10 | 16 | 30 | 17 | |||
15 | Develop/finalize requirements traceability matrix | 11 | 14 | 28 | 16 | |||
16 | Finalize project deliverables | 2 | 2 | 3 | 2 | √ | ||
17 | Develop scope statement | 4 | 9 | 10 | 8 | √ | ||
18 | Finalize/Update WBS | 2 | 3 | 5 | 3 | √ | ||
19 | Schedule (Time) and Cost Planning | |||||||
20 | Finalize hardware/software costs | 2 | 4 | 5 | 4 | |||
21 | Update activities and duration estimates | 6 | 12 | 14 | 11 | √ | ||
22 | Human Resource Planning | |||||||
23 | Finalize resource requirements | 6 | 10 | 14 | 10 | |||
24 | Finalize project costs | 4 | 11 | 19 | 11 | |||
25 | Identify training requirements | 2 | 4 | 5 | 4 | √ | ||
26 | Complete training activities | 6 | 12 | 14 | 11 | √ | ||
27 | Quality Planning | |||||||
28 | Determine impacted quality processes | 2 | 3 | 4 | 3 | √ | ||
29 | Finalize quality management plan | 2 | 10 | 18 | 10 | |||
30 | Risk Planning | |||||||
31 | Update project risks | 3 | 6 | 12 | 7 | √ | ||
32 | Draft risk register | 2 | 3 | 8 | 4 | |||
33 | Finalize risk management plan | 2 | 4 | 7 | 4 | |||
34 | Finalize Project Plan | |||||||
35 | Finalize communications management plan | 2 | 3 | 4 | 3 | |||
36 | Finalize procurement management plan | 2 | 6 | 14 | 7 | |||
37 | Finalize stakeholder management plan | 2 | 2 | 5 | 3 | |||
38 | Finalize project schedule/cost baseline | 2 | 13 | 19 | 12 | |||
39 | Finalize project plan | 2 | 5 | 16 | 6 | √ | ||
40 | Obtain approval for project plan | 2 | 4 | 7 | 4 | √ | ||
41 | Executing | |||||||
42 | Hardware | |||||||
43 | Procure hardware from suppliers | 10 | 24 | 32 | 23 | √ | ||
44 | Software | |||||||
45 | Obtain software OS licenses | 6 | 11 | 20 | 12 | √ | ||
46 | Obtain software application licenses | 6 | 8 | 17 | 9 | |||
47 | Pilot Testing | |||||||
48 | Setup test area | 1 | 2 | 2 | 2 | |||
49 | Load software onto pilot machines | 4 | 6 | 8 | 6 | √ | ||
50 | Validate functionality | 3 | 6 | 8 | 6 | |||
51 | Deployment | |||||||
52 | Configure production hardware | 10 | 25 | 33 | 24 | √ | ||
53 | Deploy production hardware | 11 | 19 | 23 | 18 | √ | ||
54 | Load software to deployed hardware | 12 | 17 | 19 | 17 | √ | ||
55 | Testing | |||||||
56 | Validate startup on deployed hardware | 4 | 9 | 18 | 10 | √ | ||
57 | Perform OS testing | 4 | 8 | 17 | 9 | |||
58 | Perform application testing | 4 | 19 | 28 | 18 | √ | ||
59 | Obtain formal sign-off from users | 6 | 17 | 24 | 16 | |||
60 | Monitoring and Controlling | |||||||
61 | Formal Customer Review 1 | |||||||
62 | Hold formal customer review after project plan approval | 1 | 3 | 4 | 3 | √ | ||
63 | Update project plan | 4 | 10 | 20 | 11 | |||
64 | Formal Customer Review 2 | |||||||
65 | Obtain updates regarding key deliverables from project team | 5 | 18 | 22 | 17 | √ | ||
66 | Hold formal customer review after pilot testing | 5 | 7 | 11 | 7 | √ | ||
67 | Update project plan | 4 | 8 | 15 | 9 | |||
68 | Closing | |||||||
69 | External | |||||||
70 | Finalize procurement with suppliers | 5 | 18 | 24 | 17 | |||
71 | Customer Approval | |||||||
72 | Hold final customer review | 1 | 2 | 2 | 2 | √ | ||
73 | Prepare/submit final customer report | 3 | 6 | 10 | 6 | √ | ||
74 | Audit against contractual deliverables | 3 | 5 | 8 | 5 | |||
75 | Obtain final customer approval | 2 | 3 | 4 | 3 | √ | ||
76 | Internal | |||||||
77 | Hold lessons learned meeting | 1 | 1 | 1 | 1 | |||
78 | Update final internal report | 4 | 6 | 12 | 7 | √ | ||
79 | Hold project team celebration event | 1 | 1 | 2 | 1 | √ | ||
Expected Project Finish Time: | Total Critical Path Variance: | days | ||||||
days | ||||||||
Total Critical Path Standard Deviation: | days | |||||||
Probability of finishing the project in | 287 | days is | ||||||
or | ||||||||
% | ||||||||
Probability of finishing the project in | 273 | days is | ||||||
or | ||||||||
% |