UnitVcourseProject.doc

Project Management

James B. Christa

Columbia Southern University

4. Project Schedule

4.1 Activity Duration Estimates (days)

Activity Number

Activity

Predecessor

Optimistic duration

Most likely duration

Pessimistic duration

Estimated duration

1

Notify Stakeholders

1

1

1

1

2

Estimate the cost

1

1

1

1

1

3

Establish starting date

1,2

1

1

1

1

4

Engage the project team

3

2

2

2

2

5

Assess the available resources

4

7

5

8

7

6

Identify suppliers

4,5

7

5

7

7

7

Purchase equipment

6

5

5

10

5

8

Install devices

7

21

20

28

21

9

Test the system

7,8

14

14

14

14

10

Hand over the project

9

1

1

1

1

image1.jpgCritical Path

image2.png12345678910

1+1+1+2+7+7+5+21+14+1=60

The critical path is

12345678910

It takes 60 days, the longest duration.

4.2 Gantt Chart

Task

Status

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Notify Stakeholders

Estimate the cost

Establish starting date

Engage the project team

Assess the available resources

Identify suppliers

Purchase equipment

Install devices

Test the system

Hand over the project

4.3 Activity Network

Activity

Predecessor

Duration

Notify Stakeholders

1

Estimate the cost

1

1

Establish starting date

1,2

1

Engage the project team

3

2

Assess the available resources

4

7

Identify suppliers

4,5

7

Purchase equipment

6

5

Install devices

7

21

Test the system

7,8

14

Hand over the project

9

1

The post UnitVcourseProject.doc appeared first on School Core.

GET HELP WITH YOUR HOMEWORK PAPERS @ 25% OFF

For faster services, inquiry about  new assignments submission or  follow ups on your assignments please text us/call us on +1 (251) 265-5102

Write My Paper Button

WeCreativez WhatsApp Support
We are here to answer your questions. Ask us anything!
👋 Hi, how can I help?
Scroll to Top