BPM307 Tutor-Marked Assignment 01

Question 1

Your new residential development project has commenced the design stage and your client has requested for the preliminary cost plan to be based on the condominium project completed in 2019. Below is the cost plan for the said completed project with a total GFA of 50,000m 2 awarded in 3Q 2016.

Cost Plan for ABC Condominium

 

s/n Descriptions Elemental cost
1 Substructure Works $6,000,000
2 Civil & Structural Works $30,000,000
3 Walls $5,000,000
4 Wall Finishes $3,000,000
5 Floor Finishes $9,000,000
6 Ceiling Finishes $1,500,000
7 Doors and Windows $5,000,000
8 Roof and Finishes $15,000,000
9 Carpentary & Joinery $8,000,000
10 Metalworks $5,000,000
11 Sanitary & Fittings $6,000,000
12 Signages & Sundries $1,000,000
13 Mechanical Works $12,500,000
14 Electrical Works $5,550,000
15 External Works $7,500,000
Sub-Total $120,050,000
16 Preliminaries $12,005,000
Total Construction Cost $132,055,000

Table 1

Proposed Project Brief:

The total GFA for the project is 75,000m2 with an additional 25,000m 2 basement carpark. References

  • Appendix 1 – Cost references of Singapore Construction Cost Data.
  • Appendix 2 – BCA Tender Price Index

(a) State FIVE (5) assumptions in your cost estimate for the total construction cost.

(b) Prepare the elemental cost plan for the proposed development showing the elemental rates and the elemental cost for the proposed development.

(c) Derive the project unit rates for the estimated construction cost:
(i) Cost per GFA
(ii) Cost per CFA

Question 2

(a) Explain the factors contributing to the substantial increase in the construction cost unit rate as compared to the past project based on the elemental cost plan, Table 1.

(b) Advise the client on the value engineering option(s) to optimize the carpark provision for the project. In your advice, you are to explain the options and indicate the potential cost savings and assumptions based on your recommendation(s)

cta_question_1

The post BPM307 Cost Planning and Estimation Tutor-Marked Assignment 01, 2026 | SUSS appeared first on My Assignment Help SG.

Plagiarism Free Assignment Help

Expert Help With This Assignment — On Your Terms

  • Native UK, USA & Australia writers
  • 100% Plagiarism-Free — Turnitin report included
  • Deadline from 3 hours
  • Unlimited free revisions
  • Free to submit — compare quotes
PR
ProjectEssays Expert
Academic Expert · ProjectEssays

Expert academic writer and education specialist helping students in the UK, USA, and Australia achieve their best results.

Need help with your own assignment?

Our expert writers can help you apply everything you've just read — to your actual assignment, brief, and marking criteria.

Get Expert Help Now →
📝 Free Submission — No Card Required

Need Help With This Assignment?

Our verified experts deliver 100% original, plagiarism-free work to your exact brief and marking criteria. Submit free — compare quotes — choose your expert.

Write My Assignment FREE Get A Free Quote →

No credit card · No commitment · First quote in minutes